Specifications and Dimensions
19
F232228
If the existing floor is not reinforced concrete at least
6 inches (153 mm) thick over a solid foundation, cut a
hole approximately 5 feet (1.52 m) square through the
existing floor. Excavate to a depth of 6 inches
(153 mm) from the top of the existing floor. Produce a
pyramid-shaped hole by excavating the bottom of the
hole to a width 6 inches (153 mm) wider on each side
than the width of the top of the hole. Fill with 6 inches
(153 mm) of reinforced concrete. Embed the mounting
bolts or base frame as the concrete is poured. Ensure
that the bolt threads extend 2 inches (51 mm) above
floor level.
After the concrete has cured, proceed as follows:
1. Place the washer-extractor adjacent to the
foundation. Do not attempt to move the machine
by pushing on the sides. Always insert a pry bar
or other device under the bottom frame of the
machine to move it.
2. Remove the wood skid by unscrewing the
carriage bolts holding the skid to the bottom
frame of the washer-extractor.
3. Place the washer-extractor carefully over the
anchor bolts. Never attempt to lift the machine by
the door handle or by pushing on the cover panels.
4. Raise and level the washer-extractor 1/2 inch
(13 mm) off the floor on three points, using
spacers such as nut fasteners.
5. Fill the space between the washer-extractor base
and the floor with a good quality non-shrinking
machinery grout to ensure a stable installation.
Grout completely under all frame members.
(Remove front panel and metal back panel to
gain access to all frame members.) Refer to
Figures 10 through 13. Force grout under
machine base until all voids are filled.
6. Remove the spacers carefully, allowing the
machine to settle into the wet grout.
7. Before grout sets completely, make a drain
opening in the rear of the washer-extractor
grouting with a stiff piece of wire; this opening
should be approximately 1/2 inch (13 mm) wide
to allow any surface water build-up under the
base of the machine to drain away. Do not omit
this step.
8. Position the mounting bolt washers and locknuts
on the anchor bolts and fingertighten locknuts to
machine base.
9. After the grout is completely dry, tighten the
locknuts by even increments – one after the
other – until all are tightened evenly and the
washer-extractor is fastened securely to the floor.
NOTE: Check and retighten the locknuts after five
to ten days of operation and every month thereafter.
10. Check vibration safety switch and gap setting and
switch function.
Figure 10
Figure 11
PHM570N
PHM571N
PHM570N
30.5 in.
(775 mm)
7.3125 in.
(186 mm)
11 in.
(279 mm)
4.0625 in.
(103 mm)
Typical
4.0625 in.
(103 mm)
Typical
30.125 in.
(765 mm)
UW35AV
PHM571N
4.0625 in.
(103 mm)
Typical
4.0625 in.
(103 mm)
Typical
36 in.
(914 mm)
35.625 in.
(905 mm)
9.125 in.
(232 mm)
14.5 in.
(368 mm)
28 in.
(711 mm)
UW60AV
Vue de la page 20